This project was the placement of the Magnolia Street Bridge at Mile post VM121.9 in Edwards, MS. The project consisted of demolishing and disposing of the existing timber bridge; loading, hauling, and placing over 500 tons of sub ballast; over 300 CY of concrete; installation of 2,000 LF H-Piles; installation of KCS supplied brick veneered wall and coping; installation of backfill and tunnel liner; installation of erosion control fencing; and grass seeding, fertilizing, and mulching.
Beginning Date: June 2007Ending Date: March 2008